The collaboration between T.M. S.R.L. and SIEMENS continues during the modernization works of the primary cabin of Trieste Porto Vecchio for Mari & Mazzaroli, contractor for AcegasApsAmga, part of the Hera Group. The purpose of the collaboration by T.M. S.R.L. is the engineering, wiring, assembly and testing of the SIEMENS NXPLUS C medium voltage switchboards, as well as their installation on site with the ad hoc creation of an auxiliary duct.
“The renovation of the Porto Vecchio Primary Power Plant is part of a broader plan for the development of the AcegasApsAmga electricity distribution networks which, in addition to Trieste, also involves the city of Gorizia”
At the Pagazzano headquarters, supported by our technical office, the T.M. team took care of the mechanical and electrical assembly of the medium voltage panels and their testing.
The installation of the new MT panels is underway, and the adaptation to the situation on site with the creation of a custom cable duct.
We thank our customers Mari&Mazzaroli, AcegasApsAmga and the HERA Group and our technical partners SIEMENS, Cabur, Comelettric.